The second study had its kick-off meeting on 17 June 2015 and will run for a maximum of 24 months. The table below gives an indicative timeline for the coming tasks.

Please note that this timeline is subject to change and may be updated during the course of the study. Those who have registered through this website will be informed of website updates, meetings and availability of (draft) documents.

Any stakeholder meeting is subject to confirmation of room availability. Please do not make your travel arrangements before receiving the invitation and agenda about 4 weeks prior to the meeting.

Oil free and low pressure compressors

Date

Activity

17 June 2015

Project kick-off meeting

October 2015
  • Revised website www.eco-compressors.eu
  • General notification / invitation to register
March 2016 Publication (draft) Task 1-4
26 April 2016 1st Stakeholder meeting
TBD Publication (draft) Report Tasks 5-6-7-8 (for 2nd stakeholder meeting)
TBD 2nd Stakeholder meeting
April 2017 Publication Final report Task 1-8

 

 

 